PROJECT UPDATES

LAST UPDATED: October 18, 2019

Golden Age Park Grand Opening
GA.jpg

GOLDEN AGE PARK - 739 S Coronado St, Los Angeles

We are excited to share that California’s first intergenerational park started construction in March of 2019, and that demolition and underground construction have been successfully completed. Golden Age Park’s ribbon cutting event is SCHEDULED for November 2nd, 2019.

September, 2019 UPDATE: The construction team is currently wrapping up and finalizing all park installations in PREPARATION for the november 2nd grand opening event.

Golden Age Park nearing completion (October, 2019)

Golden Age Park nearing completion (October, 2019)

mAYBERRY SKATE PARK - 13201 E. Meyer Road, Whittier

CONSTRUCTION ASSOCIATED WITH THE SKATE PARK ADDITION IS SET TO BEGIN IN Summer OF 2019. MAYBERRY SKATE PARK WILL ADD APPROXIMATELY 10,000 SQUARE FEET OF NEW SKATE AMENITIES TO THE EXISTING INFRASTRUCTURE AT AMELIA MAYBERRY PARK. IMPROVEMENTS WILL INCLUDE NEW AMENITIES SUCH AS: BLEACHERS, SEAT WALLS AND MINOR RESTROOM RENOVATIONS. THE SKATE PARK’S RIBBON CUTTING EVENT IS EXPECTED TO TAKE PLACE FALL OF 2019.

october, 2019 UPDATE: Mayberry Skate Park’s concrete components/elements are nearing completion. The park’s skate bowl received its final concrete pour the week of October 14th. The construction team is now moving on to complete restroom renovations.  Landscaping and lawn restorations are expected to take place in late November. 

Concrete work nearing completion at Mayberry Skate Park (October, 2019)

Concrete work nearing completion at Mayberry Skate Park (October, 2019)


WISHING TREE PARK - 204th Street & Budlong Avenue, West Carson

Construction associated with the Neighborhood Land Trust’s largest project to-date started on may 1st, 2019, with the installation of a sound barrier to reduce construction-related noise.

With the nearest park located over two miles away, Wishing Tree Park is highly anticipated by the local community, and will serve over 8,700 residents who live within a half-mile of the site. The park’s ribbon cutting event is expected in the fall of 2020.

Completed activities related to site preparation and environmental quality include:

· Bird nesting studies

· Archaeological training of all site workers

· Installation of noise reduction barrier

·  Weed/plant removal in PREPARATION for underground work

·  Installation of erosion-control measures (pictured below)

june, 2019

The LA Neighborhood land trust was fortunate to receive a donation of 34,000 + cubic yards of soil from a site owned by the la times. the soil will be used to create a two-foot soil cover/layer at the park site as requested by community residents and stakeholders.

August, 2019

TELACU Construction Management (the park’s General Contractor) has started deep excavation work to install underground piping/utility lines associated with sewage and water. These new lines will be linked to the site’s restrooms, general park irrigation and other facilities.

September, 2019

TELACU COnstruction Management has started to bring in clean soil to distribute across the park site after project utility work is completed. Deep excavation is coming to a close and storm water DEBRIS FILTRATION EQUIPMENT is ready to be installed.

October, 2019

Underground utility installation such as storm water, site electricity and water piping is underway.  Clean soil is now being imported to the park site and stockpiled in preparation for site grading. Coordination with various easement holders and work to address unforeseen underground conditions is also in progress. We hosted the Del Amo Action Committee (DAAC) on two site visits with support from TELACU Construction Management to give community members more insight into construction progress.  Community notices are being distributed with support from the DAAC team.

WT%252Bsign.jpg
daac visit.jpg
Site visit with the Del Amo Action Committee (DAAC)

Site visit with the Del Amo Action Committee (DAAC)